Egypt Customer Site · Completed 2024

2024 Egypt Textile Dyeing Project: 6 TPH WNS Gas-Fired Steam Boiler

When an Egypt textile dyeing customer added a new production line, its existing steam supply was insufficient and steam pressure was unstable. JINHONG supplied the WNS6-1.25-Q boiler package, connected it to the line, and completed installation, commissioning and training.

ApplicationTextile Dyeing
Capacity6 TPH
Rated Pressure1.25 MPa
FuelNatural Gas
Installed 6 TPH WNS gas steam boiler at an Egypt textile dyeing plant
Actual project photo · 2024 boiler installation in Egypt

Project Brief

A steam-supply project built around a real production-line problem

This 6 TPH WNS steam boiler project in Egypt began with three confirmed conditions: a new textile dyeing line, insufficient steam supply and unstable steam pressure. JINHONG supplied the confirmed boiler package and carried out on-site installation, production-line connection, commissioning and training.

For planning a similar expansion, review the dyeing-line steam capacity and pressure checklist.

The customer’s challenge

The customer was expanding textile dyeing production with a new line. The existing steam supply was insufficient for the additional demand, while unstable pressure created a second issue for the expanded process.

JINHONG’s solution

JINHONG supplied a WNS6-1.25-Q natural gas steam boiler rated at 6 TPH and 1.25 MPa. JINHONG engineers installed the boiler, connected it to the production line, commissioned the system and provided training.

Challenge to Response

How the confirmed requirements shaped the project scope

Each engineering action below corresponds directly to a requirement confirmed for this project.

Customer needAdditional demand from a new textile dyeing line
JINHONG responseSupplied the confirmed boiler package
Customer needInsufficient steam supply
JINHONG responseSupplied a boiler rated at 6 TPH and 1.25 MPa
Customer needConnection of the boiler to the new production line
JINHONG responseCompleted production-line connection and on-site commissioning

Delivery Scope

Equipment supply backed by on-site engineering

JINHONG supplied the boiler, and its engineers carried out site connection, installation, commissioning and on-site training.

1

Boiler package

The confirmed boiler package supplied for this project.

2

Installation

On-site installation carried out by JINHONG engineers.

3

Line connection

Boiler system connected to the customer’s new production line.

4

Commissioning & training

Commissioning and training completed by JINHONG engineers.

Technical Configuration

WNS natural gas steam boiler for the dyeing line

The selected boiler uses natural gas. Its confirmed combustion configuration combines a low-NOx burner with flue gas recirculation.

  • Model: WNS6-1.25-Q
  • Steam capacity: 6 TPH
  • Rated pressure: 1.25 MPa
  • Combustion: Natural gas, low-NOx burner and FGR

See the WNS gas and oil fired steam boiler range for the product platform used in this project.

Actual Project Photos

Installed boiler and site connection details

The photographs below were taken at this project and show the installed boiler, burner, instruments and connected site piping.

Project Completion

Completed in 2024

The boiler package was installed and connected to the new production line. JINHONG engineers completed site commissioning and training as part of the project.

BoilerInstalled
Production LineConnected
CommissioningCompleted
TrainingCompleted

Project FAQ

Key facts about the Egypt boiler project

What boiler was supplied for this project?

JINHONG supplied a WNS6-1.25-Q natural gas steam boiler rated at 6 TPH and 1.25 MPa.

What problem led to the project?

A new production line created additional demand while the existing steam supply was insufficient and pressure was unstable.

What did JINHONG provide?

JINHONG supplied the boiler with a low-NOx burner and FGR. Its engineers handled installation, line connection, commissioning and training.

Planning steam supply for a new production line?